The U.S. 40 bridge maintenance project is underway from MP 3-9. Thank you for your cooperation and help to inform the public about this project! Beginning May 16, the eastbound direction will be restricted to one lane permanently while they finish the crossover configuration. The traffic crossover to eastbound lanes is scheduled to occur on May 21, at night. UDOT will let you know when it does happen. For the rest of the week, the listed traffic impacts are below.

Current Traffic Impacts

  • One lane closed in the eastbound direction from 6am-3pm during the weekdays; 6am-12pm on Saturdays
  • One lane closed in the westbound direction from 9am-6pm during the weekdays; 6am-12pm on Saturdays

Additionally, UDOT in conjunction with Heber City is beginning a repaving project on U.S. 40 from MP 12-16. This project will start on Monday, May 16, and last for two months. Crews will be working Sunday through Thursday, with some night work expected. During non-peak hours, from 400 North to 750 North, traffic will be reduced to one lane in each direction. Outside of city limits, drivers can expect two lanes of traffic in each direction with lane shifts in place. Please email [email protected] if you need any more information regarding this project.